﻿1
00:00:17,203 --> 00:00:20,412
“Vector Group, Turns Ratio and No Load” Tab

2
00:00:20,437 --> 00:00:27,921
In the device and the software provided by Vebko Company, turns ratio, vector group and no load current tests are performed simultaneously.

3
00:00:27,946 --> 00:00:35,359
To perform this test, the voltage is applied from high voltage side and the voltage of low voltage side is measured using binary inputs.

4
00:00:35,384 --> 00:00:40,359
In measuring the LV side, the voltage and its angle are measured at the same time.

5
00:00:40,384 --> 00:00:44,921
Also, to measure no load current, actual current of voltage outputs are used.

6
00:00:44,946 --> 00:00:54,218
To perform this test, first, the test method must be selected from among “LL” and “LN” from “Test Setting” section in field “Test Method”

7
00:00:54,249 --> 00:00:58,467
In fact these methods determine the type of voltage applied to the primary;

8
00:00:58,492 --> 00:01:06,842
in “LL” the voltage applied is three phase while in “LN” the voltage is applied in form of phase to null or coil to coil.

9
00:01:06,867 --> 00:01:13,475
Note that in both of these methods, the secondary voltage measurement is done in coil to coil form.

10
00:01:13,500 --> 00:01:18,678
In “Direction” section, the direction of the conversion ratio test is specified;

11
00:01:18,703 --> 00:01:32,513
the conversion ratio test direction for a three-coil transformer is “Primary to Secondary” for a conversion ratio test between primary and secondary while it is “Primary to Tertiary” for a conversion ratio test between primary and tertiary

12
00:01:32,538 --> 00:01:40,436
The test voltage is specified in “VLL” field while its corresponding phase voltage is specified in “VLE” field.

13
00:01:40,461 --> 00:01:49,413
In “Stage Time” section, the time of voltage application is specified; this time for “LL” method is the time of test while for “LN” method,

14
00:01:49,438 --> 00:01:53,834
this time equals the time of voltage application to each of the coils.

15
00:01:53,880 --> 00:01:59,374
You can see two options of “Just Result” and “All Table” in “Add to Report” drop-down field.

16
00:01:59,399 --> 00:02:05,678
By selecting “Just Result”, only those parts of the table whose test has been performed are added to the report.

17
00:02:05,703 --> 00:02:10,202
But if “All Table” is selected, the whole test table is added to the report.

18
00:02:10,227 --> 00:02:22,045
In “Read Input Voltage” field, the measurement method for the actual voltage applied from the device is specified which can be selected from among “Actual Voltage” and “Binary Input” of the device.

19
00:02:22,070 --> 00:02:27,997
In “Insert Mode” section, the settings related to inserting the number of “Taps” are adjusted.

20
00:02:28,022 --> 00:02:34,544
If you wish to insert all of the taps, you need to select “All Tap” and in “Sort Direction” field,

21
00:02:34,569 --> 00:02:42,108
specify that whether the taps are to be inserted from top to down or down to top by selecting “Up” or “Down”.

22
00:02:42,133 --> 00:02:49,694
If you wish to test a specific tap, you need to select “Specific Tap” and then enter the number of your intended tap.

23
00:02:49,719 --> 00:02:53,209
Also, if you wish to insert a specific number of taps,

24
00:02:53,234 --> 00:02:58,022
you need to select “In Range” and then specify your intended range.

25
00:02:58,047 --> 00:03:09,349
After specifying the mentioned information, by selecting “Insert Rows”, rows are inserted in the test table in accordance with the number of taps of the transformer.

26
00:03:09,374 --> 00:03:16,615
If you wish to insert a number of taps in a specific position in the table, you can use “Insert Position” section.

27
00:03:16,647 --> 00:03:22,232
For example, here taps number one and two are inserted above tap number one.

28
00:03:22,257 --> 00:03:32,841
Performing a test for a transformer with off-load tap changer: to make a test file for a “Dyn11” transformer with three taps and “Offload” tap changer,

29
00:03:32,866 --> 00:03:43,450
“LL” should be selected as the “Test Method” and 30 volts line to line should be selected as the test voltage and “Up” should be selected as the “Sort Direction” for the taps.

30
00:03:43,475 --> 00:03:47,372
Then, by selecting “Insert Rows”, the test table is created.

31
00:03:47,397 --> 00:03:51,919
To perform the test, first, you need to adjust the wiring in accordance with the picture.

32
00:03:51,944 --> 00:04:04,755
In this wiring, the voltage resources are connected to the primary side of the transformer and to measure the voltage, the secondary of the transformer is connected to the inputs of the device according to the picture.

33
00:05:16,393 --> 00:05:21,645
Next, “Apply Test” must be selected after selecting the intended row in the software

34
00:05:21,678 --> 00:05:29,864
Here, all three rows of a “Tap” are selected and then by pressing “Apply Test” the test is performed and the results are recorded.

35
00:05:29,889 --> 00:05:41,473
The results of this test are recorded in “I Prim. Meas.”, “V Sec. Meas.”, “TTR Act.”, “TTR Dev.”, “Phase Meas.” and “Phase Dev.” columns respectively.

36
00:05:41,498 --> 00:05:48,567
The mentioned parameters stand for no load current, the measured secondary voltage, the measured actual conversion ratio,

37
00:05:48,592 --> 00:05:57,512
the diversion of the conversion ratio from the specified value, the measured phase and its diversion from the actual value respectively.

38
00:05:57,537 --> 00:06:05,747
After performing the test, the results of the test are assessed in “Assessment” column based on the factors entered in “Tolerance” section.

39
00:06:05,772 --> 00:06:16,215
Considering these factors, the maximum allowed conversion ratio fault is 0.5 percent and the maximum allowed phase diversion is 5 degrees;

40
00:06:16,240 --> 00:06:26,371
since the conversion ratio fault of phase number two is above the specified amount, the assessment of this row fails and the two other phases pass.

41
00:06:26,402 --> 00:06:36,613
It is possible to view the result for any of the phases categorized as “Turn Ratio Result”, “Vector Group Result” and “Current” by selecting its corresponding row.

42
00:06:36,638 --> 00:06:45,262
Also in “Plot” section, the results of the test as well as the changes of the parameters measured in different taps are displayed in form of diagrams.

43
00:06:45,287 --> 00:06:49,058
In this section, “TTR”, “Ratio dev”, “V phase”

44
00:06:49,083 --> 00:06:57,683
“Phase dev” and “No load Current” diagrams are displayed for every phase and it is possible to remove the diagram by unchecking it.

45
00:06:57,708 --> 00:07:06,667
Performing the test for a transformer with “On Load” tap changer: There are three methods to perform a test for a transformer with “On Load” tap changer.

46
00:07:06,692 --> 00:07:12,581
“Manual” method: in this method, it is possible to select all rows of the table and then “Apply the Test”.

47
00:07:12,606 --> 00:07:19,690
After the test is finished for every tap, a message stating that “To Continue the Test, Press the Space Button” appears.

48
00:07:19,715 --> 00:07:30,667
In this case, you need to change the transformer tap manually and then continue the test by pressing the space button.This procedure continues until the last tap is tested.

49
00:07:30,692 --> 00:07:36,589
“Automatic Tap Control, By time” method: in this method which has its own wiring,

50
00:07:36,614 --> 00:07:50,180
from the “Tap Changer” command panel, you should take two contacts of “Raise” and “Lower” to the binary out of the device in accordance with what can be seen in the wiring so that after testing every “Tap”,

51
00:07:50,205 --> 00:07:57,665
the command is applied to “Tap Changer” as long as the value specified in “Impulse” field and the “Tap” change operation begins.

52
00:07:57,690 --> 00:08:04,570
By applying the “Tap” change command, after the time specified in “Time” field, the next “Tap” test begins.

53
00:08:04,595 --> 00:08:11,148
This time is allocated for waiting for the “Tap Changer” to settle on the next “Tap” of the transformer.

54
00:08:11,173 --> 00:08:15,851
This procedure continues until the last “Tap” test is performed.

55
00:08:15,884 --> 00:08:23,422
In performing this test, just like the “Manual” method, “Apply Test” is selected after selecting all of the rows.

56
00:08:23,447 --> 00:08:27,047
After applying, the test begins automatically.

57
00:08:27,072 --> 00:08:30,508
“Automatic Tap Control, By Inprogress” method:

58
00:08:30,533 --> 00:08:40,367
this method has one more step of wiring than the previous method and in addition to time, it has the condition of contact reception

59
00:08:40,392 --> 00:08:53,945
This means that, from the command panel, two contacts that indicate the state of “Tap Changer” should be brought to the input number 8 of the device so that if the “Tap” change occurs before the specified time,

60
00:08:53,970 --> 00:09:06,156
the next “Tap” test begins. In performing this test, like other methods, “Apply Test” is selected after selecting all of the rows. After applying the test, it begins automatically.
