Test View Window in Synchronizer Room

2
00:00:21,004 --> 00:00:24,539
“Shot test” is the first test that can be performed on “Synchronizer”.

3
00:00:24,564 --> 00:00:35,585
To perform this test, first you need to enter the system (1) characteristics which is a simulator of the infinite bus and the system (2) characteristics which is a simulator of the generator.

4
00:00:35,610 --> 00:00:42,773
The amount of voltage difference, frequency and angle of systems (1) and (2) are entered in “DeltaVL-L”,

5
00:00:42,798 --> 00:00:45,726
“delta F” and “delta Phi” respectively.

6
00:00:45,751 --> 00:00:52,546
The amounts of voltage, frequency and angle are specified in the column at the right side of this box.

7
00:00:52,571 --> 00:00:58,898
Note that it is possible to directly specify the voltage, frequency and phase values of the system (2)

8
00:00:58,923 --> 00:01:09,421
in which case the amount of difference between the specified values with their nominal values is displayed in the column on the left side of this box.

9
00:01:09,446 --> 00:01:17,578
In performing this test, the characteristics of system (1) is fixed and for every test point, the characteristics of system (2) change.

10
00:01:17,603 --> 00:01:29,820
Other methods to add test points include clicking on the characteristic curve and selecting “Add” or holding the ctrl key and clicking on the intended point on the characteristic curve.

11
00:01:30,084 --> 00:01:33,565
Finally, after specifying the test point,

12
00:01:33,590 --> 00:01:43,562
the test is performed and in accordance with that whether the test point is inside the characteristic or outside it, the relay issues connect or disconnect command.

13
00:01:43,587 --> 00:01:52,799
The test point assessment is done in accordance with synchrony or non-synchrony of “Nom” and “Act” columns in “Assessment” section in the test point table.

14
00:01:52,824 --> 00:01:57,799
The characteristics of system (2) / the test point is specified in “System2” section.

15
00:01:57,824 --> 00:02:03,330
Other options of this section are the same as those of the other previously mentioned rooms.

16
00:02:03,355 --> 00:02:09,447
As an example, a point inside the connection zone and another point outside this zone are selected.

17
00:02:09,472 --> 00:02:17,244
By performing the test you will see that the relay gives a close command inside the zone and does not connect outside this zone.

18
00:02:17,269 --> 00:02:21,190
The second and the most important performable test is “Synchronizer”.

19
00:02:21,215 --> 00:02:24,893
To perform this test you need 5 outputs from the relay.

20
00:02:24,918 --> 00:02:32,227
In fact, this relay has 5 main outputs and by giving the raiser or lower command for voltage and frequency,

21
00:02:32,252 --> 00:02:36,563
the act of “Synchronizing” and connecting the unit to the network is done.

22
00:02:36,588 --> 00:02:53,213
These outputs, which should be connected to the device for the test, include “V>”, “VM<”, “F>”, “F<” which are used to raise voltage, lower voltage, raise frequency and lower frequency respectively.

23
00:02:53,238 --> 00:03:00,040
In “Trigger” tab in “Binary Setting” section, the settings of related “Inputs” can be specified.

24
00:03:00,065 --> 00:03:06,674
In this section, to receive the commands such as receive voltage raise command, receive voltage lower command,

25
00:03:06,699 --> 00:03:23,211
receive frequency raise command and receive frequency lower command, “B1:V>”, “B1:V<”, “B3:F>” and “B3:F<” are used respectively.

26
00:03:23,236 --> 00:03:27,462
Also “Close Command” is used to receive the close command from the relay.

27
00:03:27,494 --> 00:03:35,579
In performing this test, the inputs are simulators of governor and “AVR” which are commanded by the relay.

28
00:03:35,604 --> 00:03:44,711
This test in this tab is done in the way that when you select a test point and run the test, the relay enters the voltage and frequency of system (2)

29
00:03:44,736 --> 00:03:51,299
to the closing zone by giving the voltage and frequency change commands and finally, gives the close command.

30
00:03:51,324 --> 00:04:07,885
About performing this test it should be noted that it is necessary to enter “Generator Model” in accordance with the system characteristics because the changes in voltage and frequency are done in accordance with the pulses sent from the relay and the settings entered in this section.

31
00:04:07,910 --> 00:04:18,510
For example, if “0.1” is entered as “delta V/delta t”, if one one-second pulse is sent from the relay to decrease the voltage,

32
00:04:18,535 --> 00:04:28,727
the voltage decreases by 100 millivolts. But if a 500-milliseconds pulse is sent, the voltage decreases by 500millivolts.

33
00:04:28,752 --> 00:04:40,947
As an example, here a test point is selected and “1v/s” and “100mHz/s” are entered as “delta V/delta t” and “delta F/delta t” respectively.

34
00:04:40,977 --> 00:04:55,203
By running the test you can see that based on the signals received by the inputs from the relay, the characteristic enters the connection zone from the outside.

35
00:05:00,945 --> 00:05:13,797
As the final point, it is necessary to know that the time of each of the tests is specified in “Fault Time” section in “Setting” which, if necessary, can be changed.
